
На стройке 30 рабочих должны выполнить залание за 6 дней. Чтобы выполнить задание досрочно,
количество рабочих увеличили на 20% На сколько дней раньше рабочие выполнили задание?

Ответы на вопрос

х рабочих-120%
х=30×120:100=36
30рабочих-6дней
36рабочих-х дней
30:36=х:6
х=6×30:36=5дней
6-5=1
Ответ:Рабочие выполнили задание на 1день раньше



Calculation of the Number of Days Saved
To calculate the number of days the workers completed the task earlier, we need to determine the original number of days required to complete the task and the new number of days with the increased workforce.
Given: - Original number of workers: 30 - Original number of days to complete the task: 6 - Increased workforce: 20%
Calculation of the Original Number of Days
To find the original number of days required to complete the task, we can use the formula:
Original number of days = Total work / Work done per day
Since the total work remains the same, we can assume that the work done per day is constant. Therefore, the original number of days can be calculated as:
Original number of days = Total work / (Original number of workers x Work done per worker per day)
Calculation of the New Number of Days
To find the new number of days required to complete the task with the increased workforce, we can use the same formula as above, but with the updated number of workers:
New number of days = Total work / (Updated number of workers x Work done per worker per day)
Calculation of the Number of Days Saved
The number of days saved can be calculated by subtracting the new number of days from the original number of days:
Number of days saved = Original number of days - New number of days
Let's calculate the number of days saved using the given information.
Calculation:
1. Calculate the original number of days: - Total work: 1 task - Work done per worker per day: 1 task / (30 workers x 6 days) = 1/180 tasks per worker per day - Original number of days = 1 task / (30 workers x 1/180 tasks per worker per day) = 6 days
2. Calculate the new number of days: - Updated number of workers: 30 workers + (30 workers x 20%) = 30 workers + 6 workers = 36 workers - New number of days = 1 task / (36 workers x 1/180 tasks per worker per day) = 5 days
3. Calculate the number of days saved: - Number of days saved = 6 days - 5 days = 1 day
Therefore, the workers completed the task 1 day earlier than the original deadline.
[[1]]


Топ вопросов за вчера в категории Математика
Последние заданные вопросы в категории Математика
-
Математика
-
Литература
-
Алгебра
-
Русский язык
-
Геометрия
-
Английский язык
-
Химия
-
Физика
-
Биология
-
Другие предметы
-
История
-
Обществознание
-
Окружающий мир
-
География
-
Українська мова
-
Информатика
-
Українська література
-
Қазақ тiлi
-
Экономика
-
Музыка
-
Право
-
Беларуская мова
-
Французский язык
-
Немецкий язык
-
МХК
-
ОБЖ
-
Психология
-
Физкультура и спорт
-
Астрономия
-
Кыргыз тили
-
Оʻzbek tili