
2 заводи за планом мали виготовити за місяць 360 верстатів. Перший завод виконав план на 112%, а
другий - на 110%, тому обида виконали за місяць на 40 верстатів більше. Скільки верстатів понад планом виготовив кожен завод окремо

Ответы на вопрос

х (деталей) - план первого завода
360-х (деталей) - план второго завода
х*1,12+(360-х)*1,1=360+40
1,12х+396-1,1х=400
0,02х=4
х=4:0,02
х=200 (деталей) - должен был изготовить первый за вод по плану
360-200=160 (деталей) - должен был изготовить второй завод по плану
200*1,12=224 (детали) - изготовил первый завод
160*1,1=176 (деталей) - изготовил второй завод
224-200=24 (детали)
176-160=16 (деталей)
Ответ: на 24 детали больше плана изготовил первый завод, на 16 деталей больше плана изготовил второй завод



Problem Analysis
We are given that two factories were supposed to produce a total of 360 machines in a month. The first factory exceeded the plan by 112%, and the second factory exceeded the plan by 110%. As a result, both factories produced 40 machines more than planned. We need to determine how many machines each factory produced above the plan.Solution
Let's assume that the first factory produced x machines above the plan. Then, the second factory produced (40 - x) machines above the plan, as the total number of machines produced above the plan is 40.According to the given information, the first factory exceeded the plan by 112%, which means it produced 112% of the planned machines. Mathematically, this can be represented as:
x = 112% of the planned machines
Similarly, the second factory exceeded the plan by 110%, which can be represented as:
(40 - x) = 110% of the planned machines
To solve this system of equations, we can convert the percentages to decimals. 112% is equivalent to 1.12, and 110% is equivalent to 1.10.
Now, we can solve the system of equations:
x = 1.12 * planned machines (40 - x) = 1.10 * planned machines
Simplifying the equations, we get:
x = 1.12 * planned machines 40 - x = 1.10 * planned machines
Let's solve these equations to find the values of x and the planned machines.
Calculation
To solve the equations, we can use algebraic manipulation. Let's start by isolating x in the second equation:40 - x = 1.10 * planned machines -x = 1.10 * planned machines - 40 x = -1.10 * planned machines + 40
Now, we can substitute the value of x in the first equation:
x = 1.12 * planned machines -1.10 * planned machines + 40 = 1.12 * planned machines
Simplifying further:
40 = 1.12 * planned machines + 1.10 * planned machines 40 = 2.22 * planned machines
Dividing both sides by 2.22:
planned machines = 40 / 2.22 planned machines ≈ 18.02
Now, we can substitute the value of planned machines back into the equation for x:
x = 1.12 * 18.02 x ≈ 20.16
Therefore, the first factory produced approximately 20.16 machines above the plan, and the second factory produced approximately (40 - 20.16) = 19.84 machines above the plan.
Answer
The first factory produced approximately 20.16 machines above the plan, while the second factory produced approximately 19.84 machines above the plan.Note: The calculations are approximations due to rounding.


Топ вопросов за вчера в категории Математика
Последние заданные вопросы в категории Математика
-
Математика
-
Литература
-
Алгебра
-
Русский язык
-
Геометрия
-
Английский язык
-
Химия
-
Физика
-
Биология
-
Другие предметы
-
История
-
Обществознание
-
Окружающий мир
-
География
-
Українська мова
-
Информатика
-
Українська література
-
Қазақ тiлi
-
Экономика
-
Музыка
-
Право
-
Беларуская мова
-
Французский язык
-
Немецкий язык
-
МХК
-
ОБЖ
-
Психология
-
Физкультура и спорт
-
Астрономия
-
Кыргыз тили
-
Оʻzbek tili